Installation · Guide

G98 and G99 explained: solar, batteries and your network operator

The difference between G98 and G99 is size. G98 covers systems up to 16 amps per phase (3.68kW single phase, 11.04kW three phase), and your network operator (DNO) is told within 28 days of commissioning. Anything bigger falls under G99, which needs the DNO’s permission before connection, and batteries count towards the total.

Mon–Fri 9:00am–5:00pm · Clear written quote before any work starts

Start here

Talk to us about solar, batteries or repairs.

Call 0800 156 0191, Monday to Friday, 9:00am–5:00pm, or send us a message through our contact page.

MCS certified

NAPIT registered

TrustMark approved

Fully insured

England, Wales & southern Scotland

Which applies

G98 or G99: which applies?

Here’s which one applies, why adding a battery often changes the answer, and what happens if you need approval. Planning one? See adding a battery to existing solar panels.

  • G98 is for small systems: up to 16 amps per phase, which on a normal single-phase home is about 3.68kW of inverter output. The network operator is notified within 28 days of the system being commissioned.
  • G99 is for anything bigger: the network operator has to give permission before the system is connected, so the application goes in before the installation.
  • It’s the inverter output that counts, not the number of panels. A large array on a small inverter can still fall under G98.
  • Your installer normally does the paperwork, for either route, but the legal responsibility sits with you as the owner. Check it’s included in your quote.

At a glance

G98 vs G99 at a glance.

  • Threshold. G98: up to 16A per phase, about 3.68kW single phase or 11.04kW three phase. G99: anything bigger.
  • When. G98: fit, then notify the network operator within 28 days of commissioning. G99: apply first. It can’t be connected until the network operator agrees.
  • Exception. Several G98 systems fitted close together within 28 days must be agreed with the network operator first.
  • Who submits. Usually your installer, though legally it’s your responsibility.
  • How long. G98 has no wait. On the G99 fast track, SSEN aims to reply within 10 working days. Where low-voltage works are needed, the network operator has up to 45 working days to quote.
  • Batteries. They count towards the total, often tipping you into G99.

Batteries

Why a battery often means G99.

Network operators count a battery in your system’s total capacity, so its output is usually added to your solar inverter’s.

  • Solar plus a battery often adds up to more than 16 amps per phase, so G99 applies even when the solar on its own was under G98.
  • Adding a battery to an older system works the same way: the new total is what matters. See will a battery affect my FIT payments?
  • A hybrid inverter that runs the panels and the battery from one unit may keep the total lower, because the inverter’s rating is what counts. See hybrid inverters explained.

Changes

Adding panels or changing an inverter.

G99 timing

How long G99 approval takes.

  • On the G99 fast track, SSEN aims to reply within 10 working days. Where low-voltage works are needed, the network operator has up to 45 working days to send a quote.
  • If the local network is short of capacity, the offer may come back with conditions, extra costs or a delay rather than a plain yes.
  • Export limitation is the usual answer. The system is set up so it can never send more than an agreed amount to the grid, even if the panels and battery could produce more. Export limitation, designed to a standard called G100, can help an application, though SP Energy Networks says supply upgrades may still be needed in some cases.

Export limits

Export limitation: staying under G98 or speeding up G99.

Export limitation stops your system sending more than an agreed amount to the grid. The equipment must meet a standard called G100. Some network operators then treat the system more simply:

  • SP Energy Networks allows a G98-type system with a battery up to 7.36kW in total if export is limited to 3.68kW per phase.
  • SSEN’s G99 fast track covers up to 32A (7.36kW) with export limited to 16A, or 60A (14.72kW) with export limited to 32A.
  • Network works can still be needed, SP Energy Networks says.

Rules differ between network operators, so we check yours at the survey.

What it means

What it means for you.

  • Allow for G99 time in your plans if you’re adding a battery or a large system. We’ll tell you at the survey which route applies.
  • Don’t connect a system that hasn’t been notified or approved. Notifying or applying is a legal requirement under the Electricity Safety, Quality and Continuity Regulations 2002.
  • Keep the paperwork with your other system documents. You may need it when you sell the house or switch export tariff. See the Smart Export Guarantee.
  • Plug-in or balcony panels have their own rules; check the product’s guidance before plugging one in.

How we help

How we help.

We handle the G98 notification or the G99 application for the solar and battery systems we fit, across England, Wales and southern Scotland, and set up export limits where they’re needed. You get a clear written quote before any work starts, and we tell you up front if approval is needed and how long it may take.

Sources: ENA, Connecting generation to the electricity networks; MCS, Notifying DNOs; Electricity North West, SSEN, SP Energy Networks and National Grid Electricity Distribution connection guidance (read 1 November 2026).

Questions

The things people ask before they ring.

Not answered here? Call 0800 156 0191, Monday to Friday, 9:00am–5:00pm.

What is the difference between G98 and G99?

G98 covers small systems up to 16 amps per phase (about 3.68kW on a single-phase home), which are notified to the network operator within 28 days of commissioning. G99 covers bigger systems, which need the network operator’s permission before they’re connected.

Do I need to tell my DNO about a solar battery?

Yes. The battery is connected to the grid, so the network operator needs to know. A battery’s output is usually added to your solar inverter’s, which often takes the total over the G98 limit and into G99.

How long does G99 approval take?

It varies. On SSEN’s G99 fast track it aims to reply within 10 working days. Where low-voltage works are needed, the network operator has up to 45 working days to send a quote.

What if the network operator says no?

After assessing a G99 application the network operator sends a quotation, which may include network works. An export limit can help, but SP Energy Networks says upgrades may still be needed in some cases.

Who fills in the G98 or G99 form?

Normally your installer. If you’re having a battery or more panels fitted, it should be part of the job.

Can I install before G99 approval?

You mustn’t connect it. SSEN says you can’t connect until its assessment is complete, and Electricity North West says the system can’t run on the grid until it gives final approval.

Does a battery count towards the 16A limit?

Yes. The ENA counts storage in the total, and SP Energy Networks includes the battery in its 7.36kW limit. So solar on a 3.68kW inverter plus a battery usually goes over G98, unless an export limit helps.

What is the G99 fast track?

A quicker G99 route for small, fully type-tested systems, batteries included. The ENA says the total can be up to 32A or 60A per phase, depending on the route. SSEN aims to reply within 10 working days.